Each questions and answers torrent of Exams-boost are edited and summarized by our specialist with utmost care and professionalism. What you get from the Construction-Manager exam training torrent is not only just passing the exam successfully, but also enlarging your scope of knowledge and enriching your future. CMAA Construction-Manager free download pdf is really trustworthy for you to depend on
Exams-boost has an unprecedented 99.6% first time pass rate among our customers.
We're so confident of our products that we provide no hassle product exchange.
| Certification Vendor: | CMAA (Construction Management Association of America) |
| Exam Name: | Certified Construction Manager Examination |
| Exam Number: | CCM |
| Exam Format: | Multiple-choice, Computer-based test (CBT) |
| Related Certifications: | Certified Associate Construction Manager (CACM) |
| Exam Price: | $340 (CMAA member) / $440 (non-member) application fee + $290 exam fee |
| Available Languages: | English |
| Real Exam Qty: | 175 (150 scored, 25 unscored pilot items) |
| Passing Score: | 67% |
| Exam Duration: | 240 minutes |
| Certificate Validity Period: | 3 years |
| Recommended Training: | Professional CM (PCM) Course CCM Build Up Course |
| Exam Registration: | Official Application Portal PSI Exam Scheduling |
| Sample Questions: | CMAA Construction-Manager Sample Questions |
| Exam Way: | Online remote proctored or in-person at PSI testing centers |
| Pre Condition: | Minimum 48 months of responsible-in-charge construction management experience; relevant bachelor's degree reduces required experience; references and application documentation required |
| Official Syllabus URL: | https://www.cmaanet.org/certification/ccm |
| Section | Weight | Objectives |
|---|---|---|
| Professional Practice | 10% | - Professional development - Leadership and communication - Legal and regulatory framework - Ethics and standards |
| Contract Administration | 10% | - Contract types and procurement - Change order management - Claims and dispute resolution - Negotiation and formation |
| Time Management | 10% | - Schedule control - Critical path method - Resource allocation and leveling - Scheduling techniques |
| Cost Management | 10% | - Cost control and forecasting - Estimation and budgeting - Financial reporting - Earned value management |
| Sustainability | 5% | - Lifecycle assessment - Resource efficiency - Environmental compliance - Green building principles |
| Quality Management | 10% | - Continuous improvement - Compliance and audits - Planning and standards - Quality assurance and control |
| Program & Project Management | 20% | - Stakeholder management - Lifecycle management - Project initiation and planning - Scope management |
| Technology | 5% | - Project management software - Emerging technologies - BIM and digital tools - Data management and analytics |
| Safety Management | 10% | - Safety planning and training - Incident investigation - Regulatory compliance - Hazard identification and control |
| Risk Management | 10% | - Insurance and liability - Identification and assessment - Monitoring and control - Mitigation and response planning |
1. A CM team on a new project which is in the pre-design phase is planning their climate resiliency strategy.
Which of the following is the team's BEST first step in this process?
A) Collect relevant data and reports.
B) Hire a commissioning agent.
C) Establish QA/QC specifications.
D) Establish a third-party certification.
2. A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month
10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million.
Which statement most accurately portrays program status?
A) On schedule, pay application accurately reflects percentage complete.
B) Behind schedule, pay application accurately reflects percentage complete.
C) Behind schedule, pay application exceeds percentage complete.
D) On schedule, pay application exceeds percentage complete.
3. A CM is milling and paving a 2-mile-long bridge with a surface that is in total failure. The owner gave the contractor October 24 as the fixed completion date. Meanwhile, the owner has promised the public that work hours would be 7am-7pm, 5 days per week and that the bridge would be completed by September 1.
The bridge deck is poured on a steel grid deck, but this type of operation has never been performed in the state and complications from weather have slowed progress. The contractor has requested to work nonstop 24/7 to meet the deadline told to the public.
The CM should
A) discuss with the owner and tell the contractor to do only 1/2 of the bridge.
B) tell the contractor they have until September 1 and can only work 7am-7pm.
C) meet with the contractor to go over realistic time frames and make a decision.
D) meet with the owner and contractor to vet all issues/options and make a decision.
4. Who owns the float in a typical project critical path schedule?
A) Owner
B) Project
C) Construction manager
D) Contractor
5. When applying BIM to a project, which method checks for interferences by searching for intersecting volumes?
A) Virtual Design and Construction (VDC)
B) Clash Detection
C) Parametric Modeling
D) BIM Integration
Solutions:
| Question # 1 Answer: A | Question # 2 Answer: B | Question # 3 Answer: D | Question # 4 Answer: B | Question # 5 Answer: B |
Thanks for your great Construction-Manager practice questions, I passed the test with a perfect score.
Thanks Exams-boost that encourage me to put all my effort in preparation of the exam.
They are so thorough and as close to a real paper as an exam tool can get! I scored real well in my Construction-Manager papers
Thank you!
Hello, I have just passed Construction-Manager exam.
Thank you so much!
Glad to pass Construction-Manager exam.
Thank you so much!
Wow, I scored 92%.
Disclaimer Policy: The site does not guarantee the content of the comments. Because of the different time and the changes in the scope of the exam, it can produce different effect. Before you purchase the dump, please carefully read the product introduction from the page. In addition, please be advised the site will not be responsible for the content of the comments and contradictions between users.
We have built a strong and professional team devoting to the research of Construction-Manager valid practice torrent. The experts of the team are all with rich hands-on experience and ever work for the international corporations. The authority and validity of Construction-Manager training torrent are the guarantee for all the candidates. Now, Construction-Manager valid exam torrent will provide you with the best suitable training material for you to study.
Or in case of failure, we have money back guarantee policy that if you fail exam after purchasing our Construction-Manager practice test engine, we will full refund to you soon if you send us your failure score scanned and apply for refund. No Pass, Full Refund!
Yes, our Construction-Manager exam questions are certainly helpful practice materials. Our pass rate is 99%. Our Construction-Manager exam questions are compiled strictly. Our education experts are experienced in this line many years. We guarantee that our materials are helpful and latest surely. If you want to know more about our products, you can download our PDF free demo for reference. Also we have pictures and illustration for Self Test Software & Online Engine version.
All our products are the latest version. If you want to know details about each exam materials, our service will be waiting for you 7*24*365 online. Our exam products will updates with the change of the real Construction-Manager test. It is different for each exam code.
All our products can share 365 days free download for updating version from the date of purchase. So don't worry. The exam materials will be valid for 365 days on our site.
We have professional system designed by our strict IT staff. Once the Construction-Manager exam materials you purchased have new updates, our system will send you a mail to notify you including the downloading link automatically, or you can log in our site via account and password, and then download any time. As we all know, procedure may be more accurate than manpower.
No. After purchase, our system will set up an account and password by your purchasing information. You can use it directly or you can change your password as you like. No need to register an account yourself.
Yes, we have money back guarantee if you fail exam with our products. Applying for refund is simple that you send email to us for applying refund attached your failure score scanned. Money will be back to what you pay. Normally we support Credit Card for most countries. Our refund validity is 60 days from the date of your purchase. Our customer service is 365 days warranty. Users can receive our latest materials within one year.
Self Test Software should be downloaded and installed in Window system with Java script. After purchase, we will send you email including download link, you click the link and download directly. If your computer is not the Window system and Java script, you can choose to purchase Online Test Engine. It is available for all device such Mac.
Yes, you can choose PDF version and print out. PDF version, Self Test Software and Online Test Engine cover same questions and answers. PDF version is printable.
Self Test Software can be downloaded in more than two hundreds computers. It is no limitation for the quantity of computers. So does Online Test Engine. You can use Online Test Engine in any device.
Over 59265+ Satisfied Customers